Auditors check Clause 8.6 of ISO 9001 one release at a time. The auditor picks an order that was delivered or a service that was completed. They ask what checks were planned before it reached the customer. Then they ask to see two things in the record: proof that the output met its acceptance criteria, and the name of the person who approved the release. Most findings are about the first one. The reason is simple: the acceptance criteria were never written down.
What the clause asks for
Clause 8.6 has three requirements: • Plan checks and carry them out at suitable stages, to confirm that product and service requirements are met. • Do not release to the customer until those checks are complete. The only exception is when a relevant authority approves the release and, where it applies, the customer approves it too. • Keep documented information about the release. It must show evidence that the acceptance criteria were met, and who authorized the release.
The acceptance criteria are set earlier in the standard. Clause 8.1 b) 2) requires them. Clause 8.3.5 c) requires design outputs to include them or refer to them. Clause 8.5.1 c) requires monitoring and measurement to confirm they have been met. Clause 8.6 is where the auditor checks that this chain leads somewhere.
Here is an example. An inspection record says "OK" against a drawing that has tolerances. This only shows that somebody looked. It has no measured value that an auditor can compare with the tolerance. We raise this finding against 8.6 a), and it often goes back to 8.1, because a record can only be as specific as the criteria behind it.
Where findings usually appear
Hold points on construction sites. On a construction site, Clause 8.6 usually takes the form of an inspection and test plan. Our construction sector page lists checking whether hold points were really held as one of the things we audit on active works. A hold point is a stage where the plan stops the work until the inspection is done. The finding we raise is an inspection request dated after the pour, or a checklist signed for an area that was already closed up. Going past a hold point means releasing the work before the planned checks were done.
The standard allows only one way around this: approval by a relevant authority and, where the contract gives the inspection to the client or its engineer, approval by the customer as well. An instruction to "keep the schedule moving" is not enough. Your system must name who holds this authority, and the record must show the decision they took. Releases that cannot be traced to a person. The second record requirement fails more quietly. Here are some common examples: • Initials on a dispatch note that nobody can identify. • One inspection stamp shared by a whole team. • An ERP system that releases an order automatically when the last operation is booked.
In all of these, the release cannot be traced to a person. A system can enforce the release step, but the record must still show which individual approved it. The authority to approve a release is a responsibility assigned under Clause 5.3. So if an auditor finds releases signed by people outside that assignment, they will raise the gap there as well. Service organizations. Some service organizations think Clause 8.6 is only for manufacturing and mark it "not applicable". This is a mistake. The clause covers products and services. A service is released when it is handed over: the maintenance job is closed, the report is issued, or the installation is commissioned. If a work order is closed without a planned check of the result against what the customer asked for, that is the service version of an unchecked dispatch. Clause 8.6 does not require someone other than the person who did the work to do the check. It requires the check to be planned at a stage you chose, and the record to show that it took place. For a service that is checked as it is delivered, that stage can be part of the delivery itself. A plan that asks for more than you do. The last common finding is a plan that is more demanding than the actual practice. Say your inspection plan promises a final inspection of every unit, or a hold point on every pour. Your own records will then be checked against that promise. If, in practice, you check by sample, the finding is about the gap between the plan and what you do. This is true even when sampling would have been a perfectly acceptable arrangement, had you planned it.
What the clause leaves to you
Clause 8.6 does not set an inspection percentage, a sampling plan, a final inspection department, a release form or a certificate of conformity. The words "at appropriate stages" mean you can place the checks wherever they make sense for your process. This includes the premises of an external provider, under 8.4.3 f). Some outputs cannot be checked by later monitoring or measurement. For these, Clause 8.5.1 f) requires the process itself to be validated, and the release then relies on the validation record. The measurements behind your evidence depend on equipment that is controlled under Clause 7.1.5. We audit that clause separately.
ISO 14001 and ISO 45001
ISO 14001 and ISO 45001 have no release clause. In an integrated system, the release record is a quality record. The environmental and OH&S controls on the same job are audited under Clause 8.1 of those standards. The clause references in this article are to ISO 9001:2015. They have not been mapped to the 2026 edition.
What we will and will not do
Under ISO/IEC 17021-1, we will not write your inspection and test plan, set your acceptance criteria, or decide who may release. Designing the arrangements that we then audit would be consultancy.
What we will do is explain what Clause 8.6 requires, and why a finding was raised against it. Our ISO 9001 certification page explains how the rest of the standard is audited. A certificate says nothing about any single delivery. The register records the standard edition, scope, status and validity dates. It never records a product.