Hierarchy of controls: what ISO 45001 auditors check

ISO 45001 clause 8.1.2 sets a fixed order for controls, elimination first and PPE last. What auditors check, and the findings a PPE-first system gets.

Published

Share this article

ISO 45001:2018 clause 8.1.2 requires you to work down a fixed order when you decide how a hazard will be controlled: eliminate the hazard, substitute less hazardous processes, operations, materials or equipment, apply engineering controls and reorganization of work, apply administrative controls including training, and provide adequate personal protective equipment. The order is a requirement of the standard. An auditor checks whether the levels above the control you chose were examined and the reasoning is available, which is why a control set that starts at PPE draws a finding even where the PPE is correctly selected, issued and worn.

Nothing in the clause requires elimination to succeed. Most hazards on a live site cannot be eliminated, and the standard does not pretend otherwise. What it requires is a process that reaches the chosen control by working down from the top, and evidence that it did.

The hierarchy appears twice, and fails differently

Clause 6.1.4 requires you to consider the hierarchy of controls when you plan actions to address the risks and opportunities determined under clause 6.1.2. Clause 8.1.2 requires processes for eliminating hazards and reducing OH&S risks using the hierarchy, in operation. A risk register can therefore satisfy hazard identification under 6.1.2 and still fail 6.1.4, because nothing in the planning stage looked above the control that was already in place when the register was written.

Clause 8.1.1 sits underneath both. Operational planning requires criteria for the processes and control of those processes in accordance with the criteria, which is the requirement that catches a hierarchy applied on paper and reversed at the work face. Where a method statement specifies edge protection and the crew is working in harnesses because the guardrail was never installed, the control selected sits a level above the control in use, and the finding is against 8.1.1 as well as 8.1.2.

The findings this clause produces

The common one is a risk assessment whose control column reads the same way on every line: PPE, toolbox talk, competent supervision. An auditor takes a single line, usually one they have just watched being worked, and asks what was considered above it. The finding is raised on the process rather than on the individual control, because the individual control may well be the right answer once the levels above it have been ruled out.

The second is misgrading. A permit to work, a signed method statement, a rule, signage and training are administrative controls. A machine guard, local exhaust ventilation, a physical barrier, a fixed anchor point and a scaffold in place of a ladder are engineering controls. Substitution means a change to the process, operation, material or equipment, so moving to a less hazardous solvent is substitution and adding respirators to the same solvent is PPE. An organization that scores each of its controls one level higher than it belongs produces a register that looks as though it has worked down the order when it has not moved.

Reorganization of work sits inside the engineering level and is the level most often skipped. Sequencing so that nobody works beneath a suspended load, or moving a task off the hottest part of the day, is a control at that level rather than a scheduling convenience. Where a seasonal midday working restriction applies to your sites, it is determined as a compliance obligation under clause 6.1.3 and its status is evaluated under 9.1.2, so the same rescheduling carries two obligations and is worth recording as a control in its own right.

Change re-opens the hierarchy, and clause 8.1.3 is where that is required. A new machine commissioned against a purchase order, a substituted material, a changed shift pattern or a new subcontractor changes the task, and the assessment for that task has to be revisited before the work runs. The failure mode is mundane: the equipment arrives, the operators are trained on it, and the control decision behind the task it replaced is never examined.

The last is the word adequate. Clause 8.1.2 asks for adequate personal protective equipment, which covers selection against the hazard, fit, condition and actual use. A half-mask respirator issued with no face-fit test, or a harness issued into an area with nothing to clip to, is a control that cannot function, and the second of those points back up to the engineering level rather than at the wearer. The standard's own note records that in many countries legal requirements include that PPE be provided at no cost to workers. Where that is the case for your sites, it is a compliance obligation under 6.1.3 and not a matter of procurement policy.

Workers exposed to a hazard have to participate in determining controls under clause 5.4, so an auditor will ask one of them how the control in front of them was chosen. An answer that does not connect to anything in the assessment tells us where the decision was actually taken.

What the clause does not require

It sets no format. There is no required matrix, no scoring scale, and no obligation to add a column headed hierarchy of controls to a risk assessment. What clause 6.1.1 does require is documented information on the risks and the processes and actions, to the extent necessary to have confidence they are carried out as planned, so the reasoning has to be recoverable somewhere an auditor can sample it. A verbal account from the one person who remembers the decision does not meet that.

Neither ISO 9001 nor ISO 14001 contains a hierarchy of controls. ISO 14001 clause 8.1 requires operational controls consistent with a life cycle perspective, with no ranked order among them. An integrated system grown outward from a quality manual arrives with a list of controls and no order applied to it, which is one of the first things we look for when ISO 45001 is added to an existing certification.

Two limits are worth stating. We will not select your controls or write your assessments, for the reasons set out on impartiality; we explain what the clause requires, why a finding was raised and what would resolve it. And the certificate evidences that you operate a process that applies the hierarchy. It carries no verdict that a particular control is adequate, and none that a workplace is safe. Only the standard edition, the scope, the sites, the status and the validity dates travel to the public register.